Landfill Construction Plan
Landfill Construction Plan
Update time:2024-11-02
Landfill Construction Plan
  • Transportation of Geomembrane:

Avoid dragging or pulling the geomembrane roughly during transport to prevent punctures from sharp objects.

  • Installation Sequence:

Begin installation from the bottom area and extend upward. Avoid stretching the geomembrane too tightly; leave approximately 1.5% slack to accommodate potential localized settlement and stretching.

For slope sections, install from the top down, taking into account the specific requirements of this project.

  • Seams and Joints:

Longitudinal seams of adjacent sheets should not align horizontally; stagger them by at least 1 meter.

Longitudinal seams should be positioned at least 1.5 meters away from the toe of the slope or corner, placing them on flat sections of the area.

  • Installation Order:

Begin with the slopes, followed by the base area of the site.

  • Orientation of Sheets on Slopes:

During slope installation, ensure the direction of the geomembrane roll is aligned roughly parallel to the line of the steepest slope.